Question: A defense contractor has just started producing turbines for a new government contract. The first turbine took 463 hours to produce. The learning curve is

A defense contractor has just started producing turbines for a new government contract. The first turbine took 463 hours to produce. The learning curve is 79.3%.

How long will it take to produce the 18th turbine?

Do not round your answer.