Question: a . Determine the critical path. A - E - G - C - D A - E - F - D A - B

a. Determine the critical path.
A-E-G-C-D
A-E-F-D
A-B-C-D
b. How many weeks will the project take to complete?
Answer is complete and correct.
\table[[\table[[Number of],[weeks]],26]]
c. Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration?
Answer is complete but not entirely correct.
\table[[Number of weeks reduced,178
 a. Determine the critical path. A-E-G-C-D A-E-F-D A-B-C-D b. How many