Question: a ) Determine the expected completion time and variance for each activity. b ) Determine the total project completion time and the critical path for

a ) Determine the expected completion time and variance for each activity. b ) Determine the total project completion time and the critical path for the project .) Determine ES, EF, LS, LF, and slack for each activity d ) What is the probability that McGee Carpet and Trim will finish the project in 40 days or less?