Question: A. Develop the material requirements plan for the next 6 weeks for items C, D and E.? B. What specific managerial actions are required in

A. Develop the material requirements plan for the next 6 weeks for items C, D and E.?
B. What specific managerial actions are required in week 1?
Question list The BOM for product A is shown in the figure on the right, and data from the inventory records are shown in the table below. In the master production schedule for product A, the MPS start row has 200 units in week 3 and 100 in week 6. Click the icon to view the inventory record data. Question 4 x/ Question 5 a. Develop the material requirements plan for the next 6 weeks for items C,D and E. Question 6 Complete the inventory record for C below. (Enter your responses as whole numbers. A response of "O" is equivalent to being not applicable.) lore InfoStep by Step Solution