A developer is pursuing a project with the following: Capital cost of project : $100,000.00 Funding from
Fantastic news! We've Found the answer you've been seeking!
Question:
A developer is pursuing a project with the following:
Capital cost of project : $100,000.00 | Funding from lenders: 80% |
Initial working Capital: $5000.00 | Interest rate on loan: 10% |
Economic life of project: 5 years | Reinvestment rate: 15% |
Residual Value (year 6) : $20,000.00 | Tax rate: 30% |
Y1 | Y2 | Y3 | Y4 | Y5 | ||
Net cash flow | 25000.00 | 30000.00 | (-16000.00) | 35000.00 | 40000.00 |
Calculate:
a. Weighted average Cost of Capital
b. The net present value of the project
c. The moified IRR d Plot the NPV Profile and determine the IRR