Question: A difference between standard costs used for cost control and budgeted costs Group of answer choices Can exist because establishing budgeted involves employee participation and
A difference between standard costs used for cost control and budgeted costs
Group of answer choices
Can exist because establishing budgeted involves employee participation and standard costs do not.
Can exist because standard costs represent what costs should be while budgeted costs represent expected actual costs.
Can exist because budgeted costs are historical costs while standard costs are based on engineering studies.
Can exist because standard costs must be determined after the budgeted is completed.