Question: Which of the following equations is used to calculate direct labor time variance? a. Direct labor time variance = (Actual direct labor hours + Standard
Which of the following equations is used to calculate direct labor time variance?
a. Direct labor time variance = (Actual direct labor hours + Standard direct labor hours) × Standard rate per hour
b. Direct labor time variance = (Actual direct labor hours + Standard direct labor hours) × Actual rate per hour
c. Direct labor time variance = (Actual direct labor hours – Standard direct labor hours) × Standard rate per hour
d. Direct labor time variance = (Actual direct labor hours – Standard direct labor hours) × Actual rate per hour
Step by Step Solution
3.31 Rating (154 Votes )
There are 3 Steps involved in it
The detailed answer for the above question is ... View full answer