Question: A document that is issued by upper management and provides the project manager with written authority to use organizational resources for project activities is called

A document that is issued by upper management and provides the project manager with written authority to use organizational resources for project activities is called a(n)
project charter
statement of work
requirements document
project plan
scope statement