Question: a) Draw a critical path method (CPM) precedence (network logic) diagram b) Calculate the project schedule. Provide the schedule in tabular form showing early/late starts

a) Draw a critical path method (CPM) precedence (network logic) diagram
b) Calculate the project schedule. Provide the schedule in tabular form showing early/late starts and finishes as well as the total float and free float for each activity.
c) Determine the critical path and show it in a network diagram
d) Draw a bar (Gantt) chart showing the total float of non-critical activities.
QUESTION #1: Given the following information about a project: Activity ID JA B Duration (days) 2 Preceded by None 3 A 8 D 6 | A E 10 B F 9 ICD G 12 D H 5 D 3 3 H 2 E K 4 F L 1 G M 2 GI N 2 j O 2 L P 4 M Q 2 N R 7 J, K, M, O S 2 T 1 Q U 3 S V 5 RTUStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
