(a) Draw a graph showing the curve for the contractor's cash flow out, the curve for...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
(a) Draw a graph showing the curve for the contractor's cash flow out, the curve for the contractor's cash flow in, and the curve for the difference. Plot $ on the vertical axis and time on the horizontal axis. Show all calculations on a Excel spreadsheet. (b) Find the cash flow out, the contractor's cash flow in, and the difference, if owner's payments are delayed four weeks. Draw a graph of this situation and compare this with (a) above. (c) How much should the contractor's fee be adjusted for part (b) if the contractor's expected rate of return is 12% Contractor's Method of Payment: (all payments are at the end of week) Labor: Paid weekly Material: Materials purchased during the month are paid at the end of the first week of the next month. Spread labor and materials evenly over activity duration. Equipment: Pavement breaker - pay upon delivery. Concrete plant - 50% when ordered and 50% upon delivery. All other equipment spread over total activity duration. Monthly payments, paid in advance. (For detour, spread over total duration of "detour install" up to end of "detour remove") Fixed Overhead: This is a G&A item; not a project cash flow Variable Overhead: Labor paid at the end of each month, material same as above, and equipment paid at the end of the month. Subcontractors: Paid one week after the contractor receives his payment from the owner for the sub's work. No retainage is held on subcontractors. Owner's Method of Payment: (one payment per month) - Total quantities for the month for the unit priced items. - 50% of detour lump sum when detour install is finished and 50% when detour remove is finished. - 45% of lights lump sum when all wiring is finished and 55% when all lights are installed. -10% retention for pay items up to and including concrete topping, no retention thereafter. - Pay request submittal is made at the end of the month. Payment is due two weeks after submittal. Additional Information: - One week is equal to 5 working days, starting on Monday. - One month is equal to 20 working days. - Assume one year is equal to 48 weeks. Cash Flow Due: 5/31/21 With the work schedule given below, the project quantities and unit prices (table 1), the contractor cost per pay item (table 2): Detour Electric Install Install Wiring Lights Start Deliver Breaker Remove Install Place Detour End Paint Pavement Base Topping Remove Deliver Plant *Schedule Concrete Plant as late as possible Table 1: Pay Item Quantity Detour Unit 1 LS $/Unit $237,500.00 Remove Payment 30000 SY $15.30 Install Base 3500 CY $206.00 Place Topping Paint Lights 3500 CY $649.00 20000 LF $3.10 1 LS $826,000.00 Table 2: Cost Item Quantity Unit Material Equip. Labor Sub. Duration (days) Detour 1 EA $32,000 $80,000 $40,000 15 Install $32,000 8 Remove Concrete Plant 1 EA $220,000 (for topping) Pavement 1 EA $128,000 25 20 Breaker Remove 30000 SY $20,000 $100,000 $108,000 40 Pavement Install Base 3500 CY $40/CY $60/CY $40/CY 30 Concrete Topping 3500 CY $220/CY $80/CY $120/CY Electric Wiring 15000 LF $260,000 Install Lights 60 EA $380,000 20 Paint Pavement 20000 1 LF $0.60/LF $0.80/LF $1.00/LF B]t]g]g| 30 40 EA $140,000 -- Quality Control (1/2 base; 12 topping) Variable $400/day $320/day $1,080/day Overhead Fixed Overhead Fee $520,000 $262,200 (a) Draw a graph showing the curve for the contractor's cash flow out, the curve for the contractor's cash flow in, and the curve for the difference. Plot $ on the vertical axis and time on the horizontal axis. Show all calculations on a Excel spreadsheet. (b) Find the cash flow out, the contractor's cash flow in, and the difference, if owner's payments are delayed four weeks. Draw a graph of this situation and compare this with (a) above. (c) How much should the contractor's fee be adjusted for part (b) if the contractor's expected rate of return is 12% Contractor's Method of Payment: (all payments are at the end of week) Labor: Paid weekly Material: Materials purchased during the month are paid at the end of the first week of the next month. Spread labor and materials evenly over activity duration. Equipment: Pavement breaker - pay upon delivery. Concrete plant - 50% when ordered and 50% upon delivery. All other equipment spread over total activity duration. Monthly payments, paid in advance. (For detour, spread over total duration of "detour install" up to end of "detour remove") Fixed Overhead: This is a G&A item; not a project cash flow Variable Overhead: Labor paid at the end of each month, material same as above, and equipment paid at the end of the month. Subcontractors: Paid one week after the contractor receives his payment from the owner for the sub's work. No retainage is held on subcontractors. Owner's Method of Payment: (one payment per month) - Total quantities for the month for the unit priced items. - 50% of detour lump sum when detour install is finished and 50% when detour remove is finished. - 45% of lights lump sum when all wiring is finished and 55% when all lights are installed. -10% retention for pay items up to and including concrete topping, no retention thereafter. - Pay request submittal is made at the end of the month. Payment is due two weeks after submittal. Additional Information: - One week is equal to 5 working days, starting on Monday. - One month is equal to 20 working days. - Assume one year is equal to 48 weeks. Cash Flow Due: 5/31/21 With the work schedule given below, the project quantities and unit prices (table 1), the contractor cost per pay item (table 2): Detour Electric Install Install Wiring Lights Start Deliver Breaker Remove Install Place Detour End Paint Pavement Base Topping Remove Deliver Plant *Schedule Concrete Plant as late as possible Table 1: Pay Item Quantity Detour Unit 1 LS $/Unit $237,500.00 Remove Payment 30000 SY $15.30 Install Base 3500 CY $206.00 Place Topping Paint Lights 3500 CY $649.00 20000 LF $3.10 1 LS $826,000.00 Table 2: Cost Item Quantity Unit Material Equip. Labor Sub. Duration (days) Detour 1 EA $32,000 $80,000 $40,000 15 Install $32,000 8 Remove Concrete Plant 1 EA $220,000 (for topping) Pavement 1 EA $128,000 25 20 Breaker Remove 30000 SY $20,000 $100,000 $108,000 40 Pavement Install Base 3500 CY $40/CY $60/CY $40/CY 30 Concrete Topping 3500 CY $220/CY $80/CY $120/CY Electric Wiring 15000 LF $260,000 Install Lights 60 EA $380,000 20 Paint Pavement 20000 1 LF $0.60/LF $0.80/LF $1.00/LF B]t]g]g| 30 40 EA $140,000 -- Quality Control (1/2 base; 12 topping) Variable $400/day $320/day $1,080/day Overhead Fixed Overhead Fee $520,000 $262,200
Expert Answer:
Related Book For
Macroeconomics Principles Applications And Tools
ISBN: 9780134089034
7th Edition
Authors: Arthur O Sullivan, Steven M. Sheffrin, Stephen J. Perez
Posted Date:
Students also viewed these accounting questions
-
A particle moves along the x - axis with its position on the axis at time t given by p ( t ) = 2 t + 4 / ( 6 t ) , 0
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
7) The second financial statement to prepare is the statement of retained eamings. To determine the ending balance of retained earnings you need to start with the opening balance as reported in the...
-
Derive a formula for the second-best relative standard to regulate a polluting monopolist.
-
In auditing Train Company, you obtain directly from the bank Trains bank statement, canceled checks, and other memoranda which relate to the companys bank account for December 2016. In reconciling...
-
In following Exercises, use the normal curve to approximate the probability. An experiment consists of 18 binomial trials, each having probability 2/3 of success. Use an approximating normal curve to...
-
Production-volume variances arise with normal-absorption and standard-absorption costing, but not with actual costing. Explain.
-
Hamleys Toy Store is on Regent Street in London. It has a magic department near the main door. Suppose that management is considering dropping the magic department, which has consistently shown an...
-
Suppose the temperature in degrees Celsius over a 9-hour period is given by T(t)=-+6t+32. a) Find the average temperature. b) Find the minimum temperature. c) Find the maximum temperature. a) The...
-
Question 8 of 13 View Policies Current Attempt in Progress -/4 Sandra Robinson owns and operates Oriole, a bakery that creates personalized birthday cakes for a child's first birthday. The cakes,...
-
In 2020, the American College of Healthcare Executives released its fifth report in a series of research surveys designed to compare the career attainments of male and female health care executives....
-
In 2012, the Alliance of Aging Research established the Healthspan Campaign, a coalition of organizations committed to solving the challenges brought about by the aging of the American population....
-
Think carefully and honestly about: (a) How you are perceived by other people generally and in particular your colleagues. (b) How confident are you in your own abilities? (c) To what extent do you...
-
GM Edgar Schein on Corporate Culture3:18 minutes https://www.youtube.com/watch?v=6ZB3jJlGWuk How has Scheins thinking on culture evolved over time? Schein says that change leaders need to learn how...
-
The spice trade first brought European explorers, most notably the Portuguese adventurer Vasco da Gama, to the shores of the Indian sub-continent in the late fifteenth century. In the mid-eighteenth...
-
The following transactions were selected from the records of OceanView Company: July 12 July 15 July 20 July 23 Sold merchandise to Customer R, who charged the $3,700 purchase on his Visa credit...
-
A container holds 2.0 mol of gas. The total average kinetic energy of the gas molecules in the container is equal to the kinetic energy of an 8.0 10-3-kg bullet with a speed of 770 m/s. What is the...
-
The accounting rate of return on the initial investment presented in question 4 is: a. 0.125 b. 0.156 C. 0.219 d. 0.375
-
For a typical \($120,000\) investment in equipment with a 5-year life and no salvage value, determine the present value of the tax shield using straight-line depreciation. Assume an income tax rate...
-
Each of the following statements is true regarding capital budgeting decisions, except: a. Capital expenditure proposals involve risk. b. Acommon error is to invest in unnecessary or overly complex...
Study smarter with the SolutionInn App