Question: (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) No file chosen (c) Develop the activity schedule for the

(a) Draw a project network. (Submit a file with a maximum size of 1 MB.) No file chosen (c) Develop the activity schedule for the project. (d) Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project? The expected completion time is weeks, which is than 1 year