Question: a ) Draw the network logic diagram. b ) Determine the critical path and project duration by Critical path analysis. c ) Calculate the Earliest

a) Draw the network logic diagram.
b) Determine the critical path and project duration by Critical path analysis.
c) Calculate the Earliest Start, Latest Start and Total Float (slack time) for each activity. Provide
sample calculations for activity I.
Summarize your calculations using the following table format:
Activity Duration IPA
A
B
6
-
(
40
 a) Draw the network logic diagram. b) Determine the critical path