Question: ( a ) Draw the precedence network. ( b ) Calculate the EST, EFT, LST and LFT of each activity using the forward pass and

(a) Draw the precedence network.
(b) Calculate the EST, EFT, LST and LFT of each activity using the forward pass and backward
pass methods.
(c) Highlight/identify the critical path in the precedence network and find the duration of entire
project.
(d) Calculate the total float and safety float for each project activity.
(e) If the activity F delays by 3 days, what will happen to the duration of entire project? What
about a delay of the activity F by 5 days?