Question: ( a ) Draw the precedence network. ( b ) Calculate the EST, EFT, LST and LFT of each activity using the forward pass and
a Draw the precedence network.
b Calculate the EST, EFT, LST and LFT of each activity using the forward pass and backward
pass methods.
c Highlightidentify the critical path in the precedence network and find the duration of entire
project.
d Calculate the total float and safety float for each project activity.
e If the activity delays by days, what will happen to the duration of entire project? What
about a delay of the activity by days?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
