Question: a) Draw the project network for the relocation project (10 marks) b) What is the expected completion time for the project (8 marks) c) What

a) Draw the project network for the relocation project (10 marks) b) What is the expected completion time for the project (8 marks) c) What is the critical path (10 marks) d) Which activities can be delayed and for how long without delaying the project completion time (9 marks) e) Develop the activity schedule for the project (3 marks)
QUESTION #3 40 MARKS The University of Technology is considering relocating its Museum and Heritage Preservation office to a new location on the campus. The project manager has identified the following activities, predecessors and activity time for the relocation project. PREDECESSOR ACTIVITY A B TIME(DAYS) 4. C 9 5 E 8 B, C B LL F 12 G E 9 H G, F 8Step by Step Solution