Question: A drilling department, which has five machines, operates 8 hours a day and 5 days a week. Utilisation has been 65% and efficiency 85%. Calculate
A drilling department, which has five machines, operates 8 hours a day and 5 days a week. Utilisation has been 65% and efficiency 85%. Calculate the weekly available time (in hours) and the effective weekly capacity of the department.