Question: A drilling robot was planned to run for 2 4 hours. The standard production rate is 5 0 0 units / hour . The robot

A drilling robot was planned to run for 24 hours. The standard production rate is 500 units/hour. The robot was down for 15 minutes to replace a worn drill bit. During that 24 hours 10500 units were produced, 300 of which had to be scrapped due to oversized holes from the worn bit. What is the approximate OEE of the equipment?