Question: A facility that operates during 4 5 0 - minute shift per day produces a product whose manufacturing process consists of tasks A , .

A facility that operates during 450-minute shift per day produces a product whose manufacturing
process consists of tasks A,..., J. Operation times for these tasks and data on predecessor tasks is
provided in the table below. The precedence of tasks is also represented pictorially in the figure
below.
a)(3 Points) What is the minimum possible cycle time for this process? 11_______________
b)(2 Points) What is the maximum cycle time for this process? 59______________________
c)(5 Points) What is the largest cycle time that will ensure a shift output of 16?
450
16=28.125; The cycle time is the floor of the number, or 28
d)(5 Points) What the number of workstations for the cycle time in part c)?59
28=2.107; Ceiling is 3
e)(5 Points) Configure the line efficiently (i.e. using the fewest possible number of workstations)
so that the shift output in part f) is ensured.
Station 1 A, B, C (5+8+9=22) Station 2 D, E, F, G, H (8+3+2+4+5=22)
Station 3 I, J (11+4=15) Tasks assigned to Station 4____________
f)(5 Points) What is the cycle time of the configuration in part e)? max{22,22,15}=22
g)(5 Points) What is the efficiency of the configuration in part e)?59
3\times 22=.894; 89%
Task
Operation time
in minutes
Predecessor
tasks
A 5 N/A
B 8 N/A
C 9 A,B
D 8 C
E 3 D
F 2 E
G 4 D
H 5 G
I 11 F,H
J 4 J
A
D
F
C
B
E
G
JI
H
A
D
F
C
B
E
G
JI
H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!