Question: A factory makes a product that has a manufacturing process consisting of tasks A , . . . , K that must be completed in

A factory makes a product that has a manufacturing process consisting of tasks A,..., K that must be completed in an order that obeys a set of precedence requirements. The following table reports the performance time in minutes/unit and the preceding task(s) for tasks A,..., K.
Task Performance Time Preceding Tasks
A 2 NA
B 4 NA
C 5 A
D 7 A, B
E 7 B
F 6 C
G 3 F
H 3 D, E
I 6 H
J 8 E
K 8 G, I, K
These tasks have been signed to six workstations as follows:
Station 1 is assigned tasks A and C
Station 2 is assigned tasks B
Station 3 is assigned tasks D and E
Station 4 is assigned tasks F and G
Station 5 is assigned tasks H and I
Station 6 is assigned tasks J and K
The line will operate for 7 hours each day. Answer the following questions:
What is the cycle time for this configuration?
The answer is a whole number.
What is the total idle time per cycle for this configuration?
The answer is a whole number.
What is the percent efficiency for this configuration?
Report as a whole number by rounding.
What is the number of units of output per day for this configuration?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!