Question: A firm has prepared the following binary integer program to evaluate a number of potential new capital projects. The firm's goal is to maximize the

A firm has prepared the following binary integer program to evaluate a number of potential new capital projects. The firm's goal is to maximize the net present value of their decision while not spending more than their currently available capital.
Max 100x1+120x2+90x3+135x4
s.t.150x1+200x2+225x3+175x4500{ Constraint 1}
x1+x2+x3+x42{ Constraint 2}
x2+x41{ Constraint 3}
x2+x31{ Constraint 4}
x1=x4{ Constraint 5}
xj={1,ifprojectjisselected
0, otherwise
Which of the constraints enforces a mutually exclusive relationship?
Constraint 5
Constraint 3
Constraint 2
Constraint 1
Constrant 4
 A firm has prepared the following binary integer program to evaluate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!