Question: A firm has prepared the following binary integer program to evaluate a number of potential locations for new warehouses. The firms goal is to maximize
A firm has prepared the following binary integer program to evaluate a number of potential locations for new warehouses. The firms goal is to maximize the net present value of their decision while not spending more than their currently available capital. Max 20x1 + 30x2 + 10x3 + 15x4 s.t. 5x1 + 7x2 + 12x3 + 11x4 21 {Constraint 1} x1 + x2 + x3 + x4 2 {Constraint 2} x1 + x2 1 {Constraint 3} x1 + x3 1 {Constraint 4} x2 = x4 {Constraint 5} xj={1, if location j is selected0, otherwisexj=1, if location j is selected0, otherwise Which of the constraints enforces a contingent relationship?