A firm is considering a project that has the following cash flow and cost of capital (r)
Fantastic news! We've Found the answer you've been seeking!
Question:
A firm is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV?
r = 12.00%,
year 0, cash flow = -1,100
year 1, cash flow = 400
year 2, cash flow = 390
year 3, cash flow = 380
year 4, cash flow = 370
year 5, cash flow = 360