A firm is considering two equally risky projects, both of which could be accepted. Project A has
Fantastic news! We've Found the answer you've been seeking!
Question:
A firm is considering two equally risky projects, both of which could be accepted. Project A has an IRR of 11%, while Project B's IRR is 14%. In addition, both Project A and Project B have a positive NPV.
Given a discount rate of 9%, which project(s) should the firm accept?
Which is correct?
Project A should be accepted.
Project B should be accepted.
Both Project A and Project B should be accepted.
Related Book For
Posted Date: