Question: A firm is evaluating a project that has a net present value of $0 when a discount rate of 10% is used. A discount rate

A firm is evaluating a project that has a net present value of $0 when a discount rate of 10% is used. A discount rate of 7% will result in a a. net present value of $0 Ob. The question cannot be answered based upon the information provided. c. positive net present value. d. negative net present value