Question: A firm uses a serial assembly system and needs answers to the following: (a) An output of 900 units per shift (7.5 hours) is desired
A firm uses a serial assembly system and needs answers to the following: (a) An output of 900 units per shift (7.5 hours) is desired for a new processing system. The system requires product to pass through four stations where the work content at each station is 30, 27, 25, and 30 seconds, respectively. What is the required cycle time for such a system? (b) How efficient is your system with the cycle time you calculated? (c) Station four changes and now requires 45 seconds to complete. What will need to be done to meet demand of 900 units (assume only 7.5 hours are available)? What is the efficiency of the new system?