Question: A firm wants to develop a level material use schedule based on the following data. What should be the setup cost? Desired lot size: 6

A firm wants to develop a level material use schedule based on the following data. What should be the setup cost?
Desired lot size:
60
Annual demand:
40,000
Holding cost:
$20 per unit per year
Daily production rate:
320
Work days per year:
250
Question 2 options:
a)
$45
b)
$0.45
c)
$4.50
d)
$500
e)
$450