Question: A fixed duration task currently has one resource assigned and a work estimate of 40 hours. Three more resources are added to the task. What

A fixed duration task currently has one resource

A fixed duration task currently has one resource assigned and a work estimate of 40 hours. Three more resources are added to the task. What is the duration of the task, after adding the extra resources? There is no duration 160 40 10