Question: A flow line has three stations. The first station has a processing time of 8 minutes, and it has 3 servers. The second has a

A flow line has three stations. The first station has a processing time of 8 minutes, and it has
3 servers. The second has a processing time of 9 minutes, and it has 4 servers. The third station has a
processing time of 6 minutes, and it has 2 servers. There is a constant arrival rate of jobs to the line.
(a)(0.5 pts) What is the raw processing time, the bottleneck rate of the line and the critical WIP of
the line?
(b)(0.5 pts) What is the maximum utilization at each station? What must occur so that maximum
utilization is achieved?
(c)(1 pt) Assume that the station with the lowest maximum utilization needs one pass of rework at
that station a certain percentage of the time. What is the maximum percentage of this rework
before the station loses its status as the one with least maximum utilization?
(d)(0.5 pts) Draw a schematic of the line in (c) using symbols from class

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!