Question: A foreman has determined processing times at a work center for a set of jobs and now wants to sequence them. The list is in
A foreman has determined processing times at a work center for a set of jobs and now wants to sequence them. The list is in order of arrival.
Using the information shown in the table, answer the following questions.
Job Job Time Days Due Date Operations
Remaining
a
b
c
d
e
f
a Determine the processing sequence using First come, first served, Shortest processing time, and Earliest due date.
Sequence for First come, first served
abcdef
Sequence for Shortest processing time
Click to select
Sequence for Earliest due date
Click to select