Question: A functional manager provides you with three estimates for his activity in your PERT network. Their estir optimistically, four weeks most likely, and twelve weeks
A functional manager provides you with three estimates for his activity in your PERT network. Their estir optimistically, four weeks most likely, and twelve weeks pessimistically. The expected time for this activi Twleve weeks Two weeks Six weeks Five weeks Four weeks