Question: A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5
A future construction project has the following activity relationships and activity time estimates (in days):
| Activity | Immediate Predecessor | To | Tm | Tp |
| A | None | 4 | 5 | 6 |
| B | None | 2 | 4 | 6 |
| C | A | 1 | 4 | 7 |
| D | B, C | 2 | 5 | 8 |
| E | B | 3 | 6 | 15 |
| F | D, E | 3 | 9 | 27 |
| G | E | 3 | 6 | 15 |
| H | F, G | 2 | 2 | 2 |
- Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as 4.32
- Please calculate the expected finish time and variance for each activity. What is the expected finish time of activity A? What is the activity variance of activity B?
- Use expected finish time of each activity to construct the network. What is the critical path of the project? (no space permitted between letters, acceptable format: ABCD) What is the expected project completion time in days? What is the variance of project completion time?
- Use expected finish time to decide ES, EF, LS, LF of each activity. What is the LF time of activity E? What is the slack time of activity G?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock