Question: A Gantt chart differs from a PERT chart in that a Gantt chart Select one: a . uses charts to break a project into a
A Gantt chart differs from a PERT chart in that a Gantt chart
Select one:
a uses charts to break a project into a series of small subactivities that each has clear beginning and end points.
b represents the quickest time in which the entire project can be finished.
c helps with event or activity sequencing to make sure that things get accomplished in time for later work to build upon them.
d shows all the interrelationships that must be coordinated for the entire project to be successfully completed.
e combines critical path method and the program evaluation and review technique.