Question: A Gantt chart indicates a . formal communication paths b . the pay scale for each task of a project C . what tasks must

A Gantt chart indicates
a. formal communication paths
b. the pay scale for each task of a project
C. what tasks must be completed at what times
d. informal communication paths
 A Gantt chart indicates a. formal communication paths b. the pay