Question: A General Contractor sues an Owner claiming it was wrongfully terminated on a project. What is the initial burden of proof? Group of answer choices

A General Contractor sues an Owner claiming it was wrongfully terminated on a project. What is the initial burden of proof?
Group of answer choices
The Owner must first show that there is an excused default.
The General Contractor must first show that it was not in default at the time of termination.
The Owner must first show that the termination was justified by default.
The General Contractor must first show that it was wrongfully terminated.