Question: A generating system contains three 20 MW generating units each with a 3% FOR and one 45 MW unit with a 6% FOR. If

A generating system contains three 20 MW generating units each with a 3% FOR and one 45 MW unit with a 6% FOR. If the peak load for a 100 day period is 75 MW, what is the LOLE and EIR for this period? Assume the appropriate load characteristic is a straight line from the 100% to the 60% points.