Question: A given project activity has the following time estimates: a = 5 b = 34 m = 19 What is the variance ( 2 )
A given project activity has the following time estimates:
a = 5
b = 34
m = 19
What is the variance ( 2 ) of this project activity's estimated duration? (Round to 2 decimal places)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts