Question: A given project activity has the following time estimates: a = 5 b = 34 m = 19 What is the variance ( 2 )

A given project activity has the following time estimates:

a = 5

b = 34

m = 19

What is the variance ( 2 ) of this project activity's estimated duration? (Round to 2 decimal places)