Question: A given project has a network that looks like the one below, with activity duration being measured in days. Assume that a following activity can
A given project has a network that looks like the one below, with activity duration being measured in days. Assume that a following activity can start the same day that its predecessor ends eg if activity A ends on day then can start on day and that the first activities start on day
What is the critical path of this project? Don't put any spaces between one letter and the next eg AGRQ
How many dys will it take to complete?
How many days of slack are there for Activity D