Question: A given project returns the following values during a 5 0 % audit. The project has accomplished $ 1 . 7 5 million of a

A given project returns the following values during a 50% audit.
The project has accomplished $1.75 million of a $4,000,000 budget. The project has expended $2,000,000 to reach this level of accomplishment, and the schedule budgeted to be finished with $1.9 million in work by this point.
Which of the following are true?
Group of answer choices
The total budget (BAC) for the project is $2,00,000+1,900,000+1,750,000
The project PCIC is 50%
The project EV is $2,00,000
The project CPI is $2,000,000/$4,000,000=50%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!