Question: A) Given the demand, the cycle time for the production of the new train set EQUALS how many seconds? (round to one decimal place) B.)

A) Given the demand, the cycle time for the

A) Given the demand, the cycle time for the production of the new train set EQUALS how many seconds? (round to one decimal place)

B.) The theoretical minimum number of workstations is?

C.) The total idle time per cycle for the process is? (whole number)

TASK, WORKSTATION NUMBER

A, STATION 1

B, STATION 2

C, STATION 3

D, STATION 4

E, STATION 4

F, STATION 5

D.) The efficiency of the assembly line with 5 workstations equals??(one decimal place)

E.) if one used 6 workstations instead of 5, the efficiency of the assembly line would be what??(one decimal place)

The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,500 units per 40-hour workweek: Performance Time (seconds) Task Predecessors A 22 B 30 A 15 A D 15 A E 10 B, C F 28 D, E am o a u t

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!