Question: A good starting point for developing time and cost estimates is a . work packages. b . past experience. c . time and motion studies.

A good starting point for developing time and cost estimates is
a. work packages.
b. past experience.
c. time and motion studies.
d. work breakdown structure.
e. task analysis.