Question: A group is working on a project. The group members get feedback telling them that they are on track and that they should continue to
A group is working on a project. The group members get feedback telling them that they are on track and that they should continue to do what they are doing. The group is receiving: a. Working behaviour b. Useless information c. Balancing feedback d. Reinforcing feedback