Question: A hammock activity is created primarily to: a. Define project scope exclusions b. Calculate variance analysis results c. Create milestones with zero duration d. Estimate
A hammock activity is created primarily to: a. Define project scope exclusions b. Calculate variance analysis results c. Create milestones with zero duration d. Estimate cost of overhead tasks across multiple phases]