Question: A hardware company is interested in developing a net requirement schedule for one of its products, a claw hammer. The beginning inventory for the product

A hardware company is interested in developing a

A hardware company is interested in developing a net requirement schedule for one of its products, a claw hammer. The beginning inventory for the product is 1500 units and the safety stock is 300 units. All product can be made from start to finish within the same week. The weekly demand over a six-week planning horizon is 400, 850, 560, 900, 600, and 700 units. What is the ending inventory in week 4