Question: A highway construction contractor has developed a base ( or deterministic ) estimate for a project of $ 1 8 , 5 0 0 ,

A highway construction contractor has developed a base (or deterministic) estimate for a project of $18,500,000. The deterministic schedule is 320 calendar days and the cost for each day of delay is $5,000. The contractor has completed a qualitative risk analysis in addition to their bid as follows.
Risk Register
\table[[Risk Description,\table[[Probability of],[Occurrence]],Cost Impact,\table[[Schedule],[Impact]]],[Delay due to extreme weather,Medium,None,Medium],[Delay due to environmental violation,Low,None,High],[Subcontractor default,Very Low,High,Medium],[Delay in material delivery,Medium,Very Low,Low]]
Probability of Occurrence
\table[[Description,Probability],[Very Low,0-2%
A highway construction contractor has developed a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!