Question: a. How long is the project likely to take? (Make sure to round all intermediate calculabions for to to two decimal places.) The project is

a. How long is the project likely to take? (Make sure to round all intermediate calculabions for to to two decimal places.) The project is expected to take 36.34 weeks. (Enter your response rounded to two decimar places.) b. What is the probability that the project will take more than 36 weeks? Rofor to the standard nommai table. The probability is 0.5948 (Enter your reaponse rounded to four decimial praces). c. Consider the path A.E.G.H.J. What is the probability that this path will exceed the expected project duration? Refer to the standard normal takle The probability is 0.0179. (Enter your response rounded to four decmal places)