Question: a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, maximum (Optimistic) demand? b. How many machines are required if the operations

a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, maximum (Optimistic) demand?
b. How many machines are required if the operations manager decides to double lot sizes?
c. If the operations manager has three machines and believes that the plant can reduce setup time by 20 percent through process improvement initiatives, does that plant have adequate capacity to meet all demand scenarios without increasing lot sizes?
Macon Controls produces three different types of control units used to protect industrial equipment from overheating. Each of these units must be processed by a machine that Macon considers to be their process bottleneck. The plant operates on two 8-hour shifts, 5 days per week, 52 weeks per year. The table below provides the time standards at the bottleneck, lot sizes, and demand forecasts for the three units. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic). The manager believes that a 30 percent capacity cushion is best. O Demand Forecast Component Pessimistic Expected Optimistic Time Standard Processing Setup (hr/unit) (hr/lot) 0.05 1.0 0.20 4.6 0.05 8.4 A B Lot Size (units/lot) 60 80 100 15,000 11,000 17,000 17,000 13,000 24,000 25,000 17,000 35,000 a. How many machines are required to meet minimum (Pessimistic) demand, expected demand, and maximum (Optimistic) demand? (Enter your responses rounded up to the next whole number.) Demand Forecast Capacity Requirement (M) Pessimistic machines Expected machines Optimistic machinesStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
