Question: a . If a project's NPV is greater than zero, then its IRR must be less than the cost of capital. b . The NPVs
a If a project's NPV is greater than zero, then its IRR must be less than the cost of capital.
b The NPVs of relatively risky projects should be found using relatively low costs of capital.
c A project's NPV is generally found by compounding the cash inflows at the cost of capital to find the terminal value TV then discounting the TV at the IRR to find its PV
d The higher the cost of capital used to calculate the NPV the lower the calculated NPV will be
e If a project's NPV is greater than zero, then its IRR must be less than zero.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
