Question: A INCLUDE A NETWORK BY NODES B WHAT WOULD BE THE AVERAGE DURATION OF THE PROJECT AND ITS VARIANCE? C IF THE PROJECT IS DESIRED

A INCLUDE A NETWORK BY NODES
B WHAT WOULD BE THE AVERAGE DURATION OF THE PROJECT AND ITS VARIANCE?
C IF THE PROJECT IS DESIRED TO BE COMPLETED IN 70 BUSINESS DAYS WITH A GUARANTEED PROBABILITY OF 95%. WHAT WOULD THE AVERAGE DURATION OF THE PROJECT BE?
Activity Precedence Optimistic More likely Pessimistic
A - 4 7 10
B - 2 4 8
C A,B 2 5 8
D C 16 19 28
E C 6 9 24
F E 1 7 13
G C 4 10 28
H D,F,G 2 5 14
I G,F 5 8 17
J H 2 5 8
K I,J 17 29 45