Question: A is a project selection methodology that converts an organization's value drivers into metrics: Project Dashboards Value matrix Weighted scoring model Balanced scorecard Question 22


A is a project selection methodology that converts an organization's value drivers into metrics: Project Dashboards Value matrix Weighted scoring model Balanced scorecard Question 22 (4 points) A would be the best choice for managing a group of related projects, such as a different types of buildings: Super project Portfolio Program Plan If it is crucial t meet time and cost goals, the must be flexible: schedule Scope Time-frame Cost Question 24 (4 points) By grouping projects into , organizations can better tie their projects to meeting strategic goals: Portfolios Applications Initiatives Business units Which of the following is not a major benefit of grouping projects into programs: Increasing Revenues Increasing authority Saving money Saving time