Question: A job requires 20 hours for the initial unit and 12.8 hours for the fourth unit. What is the learning rate? O A. 80% O

A job requires 20 hours for the initial unit and
A job requires 20 hours for the initial unit and 12.8 hours for the fourth unit. What is the learning rate? O A. 80% O B. 75% O c. 90% OD. 85% O E. 70%