Question: A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concerned about the team
A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concerned about the team not receiving direct communications from this stakeholder. Which two actions should the project manager take to improve the relationship with the stakeholder? Question 15 options: Provide training to the team on emotional intelligence and status reporting techniques Schedule regular meetings with the key stakeholder to provide updates and receive feedback Share weekly status reports with detailed information about the project and team performance Submit performance reports and task assignments to keep the stakeholder informed Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders